U.S. Court Denies Samsung, SK Hynix, and Micron’s Motion to Dismiss in DRAM Antitrust Case

icon币界网
Share
AI summary iconSummary
A U.S. federal court has denied Samsung, SK Hynix, and Micron’s motion to dismiss in a DRAM antitrust case. The lawsuit, filed in June 2026 by 17 plaintiffs from five states, alleges that the companies colluded to restrict supply and inflate prices. The court found the claims sufficiently plausible to proceed. The firms, which control over 91% of the global DRAM market, argued that their actions were driven by rising AI demand, but the judge ruled their conduct exceeded normal market responses. Meanwhile, liquidity and crypto markets remain under close regulatory scrutiny, with CFT measures increasingly shaping enforcement actions.
CoinDesk reports:

IT Home, November 15 report: According to legal media LitNews, on November 14 local time, U.S. District Judge Noel Wise of the Northern District of California dismissed the joint motion to dismiss filed by Samsung, Micron, and SK Hynix, ruling that the plaintiffs’ complaint adequately alleged a reasonable claim that the three companies entered into an illegal agreement in violation of Section 1 of the Sherman Act.

IT Home note: The judge has only denied the defendants' motion to dismiss, finding that the plaintiff's allegations are sufficiently plausible on their face, thereby allowing the case to proceed to the next stage (discovery and substantive review). No final determination has been made regarding whether the three companies have violated the law or are liable for damages.

The lawsuit was filed on June 25, 2026, by 17 consumers and small businesses from five U.S. states; according to the complaint, these consumers allege that Samsung, SK Hynix, and Micron artificially restricted DRAM supply, created a market shortage, and thereby significantly increased memory prices, harming consumers.

The complaint states that, as of the third quarter of 2025, these three major DRAM manufacturers collectively accounted for more than 91% of global DRAM market revenue.

Although the defendant argued that its prudent capacity adjustments were a natural response to the surge in demand for artificial intelligence and were no different from a previously dismissed lawsuit from 2018, Judge Wise disagreed, stating plainly: “The Court finds that this is not the case.”

In her ruling, she wrote: “However, the plaintiffs’ allegations go far beyond ‘eagles watching each other’; their claims are more akin to ‘eagles flying in formation’—which is certainly not typical behavior for eagles in their natural state.”

The indictment shows that these three manufacturers began reducing traditional memory production at the end of 2022 and shifted wafer capacity toward high-bandwidth memory (HBM) in 2023.

Without increasing total production across all three companies, this reallocation of capacity drove traditional DRAM prices up a staggering 697% within just 18 months (from the end of Q3 2024 to the end of Q1 2026). Since each GB of HBM requires three to four times the silicon wafer area of standard DDR5 memory, this move severely constrained memory supply for the consumer and PC markets, casting a dark cloud over the entire industry and causing widespread hardship.

Judge Wise noted in the ruling that the three parties indeed took several coordinated actions that went beyond normal market behavior, and these measures would have been extremely difficult to reverse absent prior collusion.

Specifically, Samsung and SK Hynitz refused to sign long-term agreements with traditional DRAM's major buyers, while postponing or halting plans for new DRAM wafer fabs. Additionally, all three companies gradually reduced and shut down their DDR4 production lines during the same quarter of 2025, with Micron announcing on December 3, 2025, the closure of its Crucial consumer storage brand, which had been in operation for nearly 30 years.

The court also noted that Samsung, SK Hynix, and Micron implemented identical customer review mechanisms in January 2026 and had prior histories of price manipulation between 1998 and 2002.

Based on the above facts, Judge Wise has ordered the three DRAM manufacturers to file their formal responses to the complaint by December 7, 2026, and has scheduled the initial case management conference for January 12, 2027.

Disclaimer: The information on this page may have been obtained from third parties and does not necessarily reflect the views or opinions of KuCoin. This content is provided for general informational purposes only, without any representation or warranty of any kind, nor shall it be construed as financial or investment advice. KuCoin shall not be liable for any errors or omissions, or for any outcomes resulting from the use of this information. Investments in digital assets can be risky. Please carefully evaluate the risks of a product and your risk tolerance based on your own financial circumstances. For more information, please refer to our Terms of Use and Risk Disclosure.