SpaceX Proposes $24 Billion Texas Supercomputer Project with Gas-Fired Power Plant

iconNS3
Share
AI summary iconSummary
SpaceX has made a project announcement for a $24 billion supercomputer project in Starbase, Texas, including a gas-fired power plant and data center. The project will use 35 turbines to generate 748 megawatts and is part of the company’s push into AI. SpaceX is seeking a property tax abatement and plans a public hearing on Dec. 9. The project funding news highlights a cost 17 times the value of SpaceX’s current bitcoin holdings. New Texas leadership has paused new data center approvals for regulatory review.

SpaceX plans to spend $24 billion on a supercomputer project in Starbase, Texas. The City Notice says SpaceX proposes to build, own and operate a gas-fired power plant and a supercomputing facility. The project would combine a natural gas power plant with a data center. Starbase lies in Cameron County and developed around SpaceX's principal rocket factory and launch site.

The proposed power plant would reportedly use 35 turbines to generate 748 megawatts. Most AI data centers instead obtain electricity through the local grid. The City Notice gives no reason for SpaceX's proposed power plant. Anthropic recently agreed to purchase 1.7 gigawatts of gas-fired generators for $3.4 billion. One gigawatt equals 1,000 megawatts.

SpaceX holds 18,712 bitcoin valued at about $1.39 billion at the time of writing, according to Bitcointreasuries.net. The project's proposed cost is approximately 17 times the value of those holdings. SpaceX went public in June through the largest IPO in history. SpaceX's expansion into AI is recent. In February, Elon Musk combined xAI, Musk's AI company, with SpaceX through a stock swap that valued the combined business at about $1.25 trillion.

SpaceX has asked the City of Starbase for a property tax abatement. The requested abatement would reduce SpaceX's property taxes and permit SpaceX to use the Cameron County Enterprise Zone for the project. The city commission plans to hold a public hearing on the request on Dec. 9.

Global Commodity Trader Index, a benchmark for institutional commodity trading firms, said the AI expansion is increasingly driving demand for gas. The index said technology companies are securing generation capacity and scarce equipment directly rather than waiting for utilities to supply power. The index said data centers are becoming an important source of long-term demand for gas producers, turbine manufacturers and pipeline operators.

Democrat Gina Hinojosa defeated Republican incumbent Greg Abbott in the Texas governor's election on Nov. 3. Hinojosa campaigned against AI data centers and accused Abbott of allowing the power-intensive facilities to proliferate. Abbott ordered a pause on Aug. 3 that blocks additional data centers from advancing through the state grid operator's connection process until regulators complete an audit.

The statewide audit includes on-site power generation. The audit includes a regulatory examination of effects on local water and communities, irrespective of the energy source's location. Whether SpaceX's proposed power plant will allow SpaceX to avoid the regulatory hurdle remains uncertain.

Disclaimer: The information on this page may have been obtained from third parties and does not necessarily reflect the views or opinions of KuCoin. This content is provided for general informational purposes only, without any representation or warranty of any kind, nor shall it be construed as financial or investment advice. KuCoin shall not be liable for any errors or omissions, or for any outcomes resulting from the use of this information. Investments in digital assets can be risky. Please carefully evaluate the risks of a product and your risk tolerance based on your own financial circumstances. For more information, please refer to our Terms of Use and Risk Disclosure.