Odaily Planet Daily report: SK Hynesis is accelerating the construction of its Cheongju P&T7 advanced semiconductor packaging facility, bringing forward the commissioning of its first cleanroom by approximately three months. According to industry insiders on July 23, SK Hynesis now expects to commission its first cleanroom at P&T7 as early as July 2027, having previously targeted October 2027.
An industry insider revealed: "SK Hynix recently initiated the bidding process for the P&T7 cleanroom utilities and infrastructure projects ahead of schedule. Internally, the company anticipates that the cleanroom's commissioning will be accelerated by approximately one quarter." Some equipment-related bidding projects failed to attract bidders and are currently being reissued. Industry insiders expect all utilities and infrastructure bidding to be completed by around August. (Science and Technology Daily)