Nvidia signs $20B AI data center lease with Hut 8 in Texas, part of AI + crypto news. The two 15-year deals, signed in May and July 2026, total $19.6 billion in base value. Hut 8 must build infrastructure aligned with Nvidia’s DSX design for AI workloads. The agreements could hit $50.2 billion with renewal options. Inflation data remains a key factor for investors tracking crypto and tech sector moves.

A former Bitcoin miner just landed one of the largest data center lease agreements in history. Nvidia has been identified as the undisclosed high-investment-grade tenant behind two 15-year leases at Hut 8’s Beacon Point AI campus in Nueces County, Texas, according to a Financial Times report published July 28, 2026.

The base value of the two leases combined sits at $19.6B. If renewal options are exercised, that number climbs to $50.2B.

What exactly was signed

The deal breaks down into two phases, each covering 352 megawatts of IT capacity, for a combined 704 MW across the full campus.

The first lease, valued at $9.8B, was signed on May 6, 2026. The second followed around July 20, 2026, with a matching structure and value.

Advertisement

Both agreements require Hut 8 to build infrastructure conforming to Nvidia’s DSX reference architecture, a design framework tailored specifically for hyperscale AI workloads including model training and inference at scale.

The end goal is a full 1 gigawatt data center campus.

Hut 8’s stock surged nearly 30% in mid-May following news of the first lease.

What this means for investors watching the space

A 15-year commitment from an investment-grade counterparty provides long-duration revenue visibility that reduces Hut 8’s exposure to crypto price cycles.

The potential $50.2B total value, inclusive of renewals, reframes how investors should think about asset valuations in the former mining sector. A company’s kilowatt-hour capacity and grid interconnect position are no longer just inputs to a mining profitability model but real estate assets with a legitimate claim to hyperscaler-grade tenants.

Construction execution risk is real. A 704 MW campus built to a specific proprietary architecture is an enormously complex undertaking, and delays or cost overruns would hit Hut 8 before they hit Nvidia.

There is also concentration risk. Two leases with one tenant means Hut 8’s Beacon Point revenue story lives or dies on that relationship.

Disclaimer: The information on this page may have been obtained from third parties and does not necessarily reflect the views or opinions of KuCoin. This content is provided for general informational purposes only, without any representation or warranty of any kind, nor shall it be construed as financial or investment advice. KuCoin shall not be liable for any errors or omissions, or for any outcomes resulting from the use of this information. Investments in digital assets can be risky. Please carefully evaluate the risks of a product and your risk tolerance based on your own financial circumstances. For more information, please refer to our Terms of Use and Risk Disclosure.