The Nuclear Regulatory Commission issued a construction permit on Nov. 9 for four X-energy Xe-100 reactors at Dow's Seadrift chemical manufacturing site in Texas, advancing a project intended to supply both electricity and high-temperature steam.
The proposed Long Mott Generating Station would replace electricity and steam assets nearing the end of their lives, Dow said. The NRC says the facility would primarily generate steam for industrial use, with excess electricity exported to the grid.
The permit authorizes construction, not operation. Long Mott Energy, Dow's wholly owned subsidiary developing the project, must obtain a separate NRC operating license before loading fuel or running the reactors. Dow has not made a final decision to build the plant.
The NRC's project description lists the four-module design at 800 megawatts thermal and 320 megawatts electric. Each module can produce 80 megawatts of electricity or approximately 200 megawatts thermal of steam, making industrial heat—not just power generation—a central use of the plant.
The agency called it the first U.S. construction permit for a high-temperature gas-cooled reactor in nearly 60 years and its first approval of a multimodule advanced reactor facility. NRC Chairman Ho K. Nieh said the agency delivered on its 18-month review schedule.
Construction Still Depends on Dow
Dow said engineering and design finalization and board review remain ahead of construction. If approved, building could begin later this decade, with startup early next decade. X-energy said Dow is expected to consider a preliminary investment decision in 2027; full-scale nuclear construction would follow a final investment decision.
For later customers, X-energy says Long Mott can serve as a reference plant for subsequent Xe-100 applications, with approved generic technical reports available for reuse. Its planned projects include the Cascade Advanced Energy Facility with Amazon and Energy Northwest. Each later application would still be reviewed individually.
Dow's next decision turns on more than the permit. Edward Stones, its business vice president for Energy & Climate, said the company would evaluate “competitiveness, execution readiness, and capital affordability” before deciding whether to construct the facility.