Benzinga Pro data showed Nebius Group shares down 9.78% at $116.05 at publication on Friday. The decline followed a nearly 17% drop on Thursday as investors assessed a reduced 2026 revenue outlook and delays affecting data centers. NVIDIA CEO Jensen Huang's resignation also weighed on neocloud stocks. A larger loss at competitor Nscale added pressure on the sector.
However, Rosenblatt Securities analyst John McPeake kept a Buy rating and a $304 price target for Nebius on Thursday. McPeake said Nebius surpassed expectations across all major third-quarter performance measures. Revenue increased more than sixfold from a year earlier and exceeded McPeake's forecast by 7%. EBITDA, meaning earnings before interest, taxes, depreciation and amortization, exceeded McPeake's estimate by 57%.
Nebius reduced the company's 2026 revenue forecast because of delays at the Vineland, New Jersey, data center. McPeake described the delay as a "slight blemish" against otherwise strong third-quarter results and prospects. Microsoft has reserved most of the 300-megawatt Vineland facility under an agreement worth $17.4 billion through 2031. McPeake said landlord DataOne ended temporary diesel power operations sooner than expected, postponing the facility's rollout. Nebius expects operations at the site to begin in 2027. McPeake expects only a temporary disruption. McPeake believes strong AI demand could enable Nebius to obtain higher prices if Microsoft canceled the agreement.
Customer prepayments funded the entirety of Nebius' capital expenditures in the third quarter. Nebius expects customer prepayments and asset-backed financing to cover 75% to 85% of capital spending in 2027. Nebius has more than $40 billion in investment-grade contract revenue that could enable further financing.
Nebius increased the midpoint of the company's 2026 capital spending forecast by 20% to support new capacity exceeding 1 gigawatt. Nebius projects capital expenditures of $40 billion to $50 billion for 2027. McPeake had estimated $30 billion in 2027 capital expenditures. Wall Street had forecast $28 billion for that spending. Nebius expects to reach pretax break-even in the fourth quarter of 2027. Analysts had previously projected a pretax loss of $347 million.
McPeake expects forecasts to remain volatile while Nebius expands operations. However, McPeake slightly increased his overall estimates.
Nebius Stock Drops 9.78% Amid Revenue Outlook Cut and Data Center Delays
BenzingaShare
Nebius Group (NASDAQ:NBIS) shares dropped 9.78% to $116.05 on Friday, following a 17% decline on Thursday. The fall came after the company cut its 2026 revenue outlook and faced delays at a New Jersey data center. Analyst John McPeake of Rosenblatt Securities kept a Buy rating with a $304 price target, pointing to a sixfold revenue rise and a 57% EBITDA beat in Q3. McPeake called the data center delay a 'slight blemish' and expects only a short-term impact. On-chain data shows continued interest in the stock despite the recent turbulence. Inflation data remains a key watchpoint for investors.
Source:Show original
Disclaimer: The information on this page may have been obtained from third parties and does not necessarily reflect the views or opinions of KuCoin. This content is provided for general informational purposes only, without any representation or warranty of any kind, nor shall it be construed as financial or investment advice. KuCoin shall not be liable for any errors or omissions, or for any outcomes resulting from the use of this information.