Lithium Americas Raises Thacker Pass Project Cost Estimate by $900M

iconBenzinga
Share
AI summary iconSummary
Lithium Americas announced a project announcement on November 12, 2026, raising the Thacker Pass Phase 1 capital cost estimate by $900 million to $3.83 billion. The increase reflects higher labor, logistics, and tariff costs. The company added $150 million in contingency and expects $650 million from General Motors and $315 million from the U.S. Department of Energy for project funding news. Construction remains on track for late 2027 mechanical completion and production in 2028.

Lithium Americas announced on Wednesday that the estimated capital cost for Thacker Pass Phase 1 had risen from $2.93 billion to $3.83 billion. The nearly $900 million increase amounts to roughly 31%. Lithium Americas cited higher labor expenses, tariffs and logistics costs. The increase also reflects stronger competition for skilled workers, more expensive installation and additional construction staffing needs.

Lithium Americas added approximately $150 million in contingency funding for remaining project risks. The company increased the 2026 capital expenditure forecast from $1.3 billion to $1.6 billion to a new range of $1.7 billion to $2 billion.

Lithium Americas estimates that the revised project costs create an additional funding requirement of approximately $995 million. The company expects $650 million in contributions to the joint venture with General Motors to help meet that requirement. Lithium Americas expects another $315 million to come from existing U.S. Department of Energy loan reserve accounts. Expected amendments to the federal loan agreement would lower certain reserve funding requirements by approximately $30 million. Lithium Americas held approximately $1.3 billion in cash and restricted cash as of September 30, including $359.5 million at the joint venture.

However, Lithium Americas left the construction schedule unchanged despite the cost increase. The company expects Phase 1 to reach mechanical completion in late 2027. Lithium Americas expects production to ramp up in 2028. The fully operational facility is designed for annual output of approximately 40,000 metric tons of battery-quality lithium carbonate. Engineering work has finished, and procurement of equipment and materials is more than 90% complete. CEO Jonathan Evans said Lithium Americas remains focused on finishing construction and moving Thacker Pass into commercial production.

Thacker Pass is in Nevada and has support from a federal Department of Energy loan and a joint venture with General Motors. Nearly 2,000 workers are employed at the project, which is among Nevada's largest construction sites. Lithium Americas has described Thacker Pass as "America's largest fully integrated source of domestic battery-quality lithium carbonate" and the nation's "clearest near-term path to a reliable domestic supply."

The cost announcement preceded Lithium Americas' third-quarter earnings report, which is scheduled for Friday, November 13. Benzinga Pro data showed Lithium Americas shares down 7.52% at $1.74 at publication time on Wednesday.

Disclaimer: The information on this page may have been obtained from third parties and does not necessarily reflect the views or opinions of KuCoin. This content is provided for general informational purposes only, without any representation or warranty of any kind, nor shall it be construed as financial or investment advice. KuCoin shall not be liable for any errors or omissions, or for any outcomes resulting from the use of this information. Investments in digital assets can be risky. Please carefully evaluate the risks of a product and your risk tolerance based on your own financial circumstances. For more information, please refer to our Terms of Use and Risk Disclosure.