EdgeConneX Seeks $2.5B Financing for Meta's 1-Gigawatt Ohio Data Center

iconCryptoBriefing
Share
AI summary iconSummary
EdgeConneX is seeking $2.5 billion in financing to build a 1-gigawatt data center in New Albany, Ohio, for Meta. The Prometheus project bundles construction and power assets into one financial package. Inflation data remains a key factor in large-scale infrastructure deals. The project could influence new token listings tied to data center assets.

EdgeConneX is working to syndicate roughly $3 billion in loans to build a 1-gigawatt data center campus in New Albany, Ohio, purpose-built for Meta Platforms. The project, called Prometheus, represents one of the largest single-site data center financing efforts to date and introduces a financial structure the industry hasn’t really seen before: bundling the facility construction and its dedicated power assets into one package.

Banks including Natixis, MUFG, and Societe Generale began marketing the debt in early April 2026. The deal underscores a broader reality reshaping the data center industry: it’s no longer enough to just build the buildings. You need to finance the electricity too.

A new financing playbook for a power-hungry industry

The traditional approach to funding data centers treats the real estate and the energy supply as separate problems. EdgeConneX is merging them. By integrating off-grid power assets directly into the loan structure, the company is effectively telling lenders that the data center and its power source are a single, inseparable investment.

Advertisement

For Meta, the arrangement supports its aggressive AI infrastructure strategy. The company needs enormous compute capacity for training and running large language models, and a 1-gigawatt campus is the kind of facility that can deliver it.

EdgeConneX, backed by private equity firm EQT Infrastructure, has been on a growth tear. The company operates over 90 data centers globally and has tripled its capacity since EQT acquired it in 2020.

Why power is the new land grab

Multi-billion-dollar power-related costs have become a defining feature of new hyperscale projects. Wholesale electricity prices have climbed steeply in key data center markets, and grid connections can take years to secure.

EdgeConneX has also demonstrated interest in sustainability-linked financings in the past. Whether the Prometheus deal carries explicit green covenants hasn’t been detailed, but the company’s track record suggests environmental commitments remain part of its financing strategy even as the sheer scale of energy consumption grows.

What this means for the infrastructure investment landscape

The $3 billion Prometheus financing could become a template. If lenders are comfortable underwriting bundled data center and power assets as a single credit, it opens the door for other developers to replicate the structure, representing a broader industry trend of integrating funding for real estate and energy assets to expedite data center development.

The syndication process itself will be closely watched. How quickly the banks can place $3 billion in data center debt will reveal a lot about lender appetite for this type of exposure.

Disclaimer: The information on this page may have been obtained from third parties and does not necessarily reflect the views or opinions of KuCoin. This content is provided for general informational purposes only, without any representation or warranty of any kind, nor shall it be construed as financial or investment advice. KuCoin shall not be liable for any errors or omissions, or for any outcomes resulting from the use of this information. Investments in digital assets can be risky. Please carefully evaluate the risks of a product and your risk tolerance based on your own financial circumstances. For more information, please refer to our Terms of Use and Risk Disclosure.