This edition of CNBC’s Property Play was originally written by Diana Olick. Property Play covers emerging and evolving opportunities for real estate investors, serving individual investors, venture capital firms, private equity funds, family offices, institutional investors, and large public companies. Subscribe to receive future issues directly in your inbox.
This year, demand for large data centers in the U.S. has surged significantly due to the computing power required by artificial intelligence, far exceeding the availability of land for power supply and the workforce needed to construct these facilities, thereby increasing pressure and risk for contractors.
A new report by global project management firm Turner & Townsend shows that all these factors combined have driven costs up by 13% year-over-year—more than double the global average increase. This year’s rise is approximately three times the average annual increase over the past decade.
The report examined over 500 projects under construction or recently completed across 62 global markets and surveyed 400 experts in the global data center industry.
The report states that although cost inflation has stabilized this year, it is insufficient to offset the immense pressure from surging demand and accelerated construction and delivery timelines.
Paul Barry, Head of Data Centers for Turner & Townsend in North America, said: “More aggressive schedules will inevitably lead contractors and subcontractors to build in greater risk buffers into their pricing—whether through acceleration payments, additional overtime and labor attraction costs, or simply higher fees due to delivering at a faster pace than traditional timelines.”
He added that all these factors, combined with surging demand and supply chain pressures, will translate into higher costs.
A recent PwC report shows that global data center capital expenditures are expected to rise from approximately $800 billion this year to $1.8 trillion annually by 2050. The United States is projected to account for nearly half of global AI infrastructure investment, encompassing both data centers and chips.
Electricity is, of course, critical to all data centers. Among global respondents from Turner & Townsend, 56% identified electricity as a major obstacle to project delivery. Slightly more than half of respondents said utility access typically takes one to two years, and nearly one-third reported it takes more than two years. Electricity costs vary by region—based on a typical 60 MW design, the cost is $15.01 per watt in Silicon Valley and $10.51 per watt in Dallas.
As with all types of construction in the United States, labor remains a significant constraint. Slightly more than a quarter of respondents indicated that contractor capacity—the ability to manage backlogged projects—is sufficient.
Barry indicated that, going forward, he expects costs to moderate, with potential increases next year ranging between 6% and 10%. Many large projects have already been initiated or are in the process of starting, so cost risks have already been factored into these contracts.
Barry said: "If this demand continues, project commencements will keep increasing, and so on—but I believe we already experienced a significant surge in 2026, particularly in the procurement of new large-scale projects."