Core Scientific announced during its Q3 earnings call that it will exit bitcoin mining by year-end, shifting focus to colocation. Management confirmed the wind-down will finish in Q4, with self-mining revenue dropping 79% to $12.3 million. Colocation revenue rose nearly 60% to $215.4 million, making up 92% of total revenue. The firm is expanding colocation capacity to 485 megawatts and redirecting resources toward AI and high-performance computing. Traders are analyzing on-chain trading signals to assess the risk-to-reward ratio of this strategic shift.

Core Scientific management said on Thursday's third-quarter earnings call that the company expects to finish leaving bitcoin mining by year-end. Management said Core Scientific would begin 2027 exclusively as a high-density colocation provider. Chief Financial Officer Jim Nygaard placed completion of the mining wind-down in the fourth quarter. Chief Executive Officer Adam Sullivan also identified year-end as the expected completion date.

The earnings exhibit filed with the SEC shows colocation revenue reached $215.4 million in the quarter ended September 30, increasing nearly 60% sequentially. The exhibit shows digital asset self-mining revenue dropped about 79% from $57.4 million a year earlier to $12.3 million. Hosted mining for other customers generated $5.2 million. Colocation contributed roughly 92% of total revenue of $232.9 million.

Self-mining recorded a quarterly gross loss of $7.5 million. Colocation produced gross profit of $128.4 million and a 60% gross margin. Adjusted EBITDA rose more than threefold sequentially to $133.6 million. The adjusted EBITDA margin increased from 25% to 57%.

Nygaard said Core Scientific operated nearly 50% fewer miners at September's end than at year-end 2025. Core Scientific has redirected power and floor space toward AI and high-performance computing workloads under long-term customer agreements. Core Scientific's investor materials describe that conversion as proceeding "as circumstances allow." Other publicly traded miners have sold bitcoin and leased campuses to AI tenants. Research notes have identified a growing funding divide between miners able to finance data center construction and miners unable to do so.

Core Scientific was billing for 485 megawatts of colocation capacity as of September 30, an increase of 90 megawatts during the quarter. That capacity represented more than $700 million in average annualized colocation GAAP revenue. Sullivan said roughly 100 megawatts remaining in the CoreWeave buildout was undergoing commissioning and was expected to begin generating recognized revenue over the next few months.

CoreWeave has contracted for 590 megawatts. Core Scientific also has an AMD-backed agreement covering 530 megawatts across five campuses. Initial delivery under the AMD-backed agreement is targeted for the first half of 2027, with full delivery targeted by the end of 2028. The CoreWeave and AMD-backed relationships together cover about 1.1 gigawatts. Management expects that portfolio to generate $1.8 billion in average annual run-rate revenue once fully delivered and billing. Management expects the same portfolio to produce $1.6 billion in net operating income under those conditions.

Core Scientific held digital assets worth $2.7 million on September 30, compared with $49.7 million three months earlier and $222 million at year-end 2025. Core Scientific had continued adding bitcoin earlier this year while also selling bitcoin during the transition. Core Scientific recorded a $41.9 million contract-termination loss in the second quarter after deciding to end a Block/Proto mining chip supply agreement. Core Scientific finished the third quarter with about $1.7 billion in liquidity, including roughly $800 million in cash, following substantial capital spending on AMD sites and the Polaris acquisition.

Sullivan said the mining wind-down would simplify Core Scientific's business toward "more attractive long-term growth opportunities." Nygaard said beginning 2027 without mining results should help investors assess the underlying colocation run-rate more clearly. Core Scientific still faces the test of shutting down the remaining mining machines on schedule during the fourth quarter. Timely completion of the AMD financing package is another test for continued growth after the mining exit.

Disclaimer: The information on this page may have been obtained from third parties and does not necessarily reflect the views or opinions of KuCoin. This content is provided for general informational purposes only, without any representation or warranty of any kind, nor shall it be construed as financial or investment advice. KuCoin shall not be liable for any errors or omissions, or for any outcomes resulting from the use of this information. Investments in digital assets can be risky. Please carefully evaluate the risks of a product and your risk tolerance based on your own financial circumstances. For more information, please refer to our Terms of Use and Risk Disclosure.