Nvidia Signs $50 Billion Texas Data Center Leases for AI Infrastructure

iconCryptoBriefing
Share
AI summary iconSummary
Nvidia signs $50 billion Texas data center leases for AI infrastructure, expanding AI + crypto news coverage. The 15-year deal with Hut 8 includes a base value of $19.6 billion and spans 704 megawatts. A second phase added 235 megawatts, raising total IT capacity to 949 megawatts. Nvidia plans to sublease parts of the facility. Inflation data remains a key factor for investors tracking the sector.

Nvidia just locked in one of the largest data center deals ever. The company signed leases worth up to $50 billion for Hut 8’s Beacon Point AI data center campus in Nueces County, Texas, a facility designed to house hundreds of thousands of its own graphics processing units.

The deal spans two long-term leases covering 15 years, with a base contract value of $19.6 billion and renewal options that could push the total to $50 billion.

How the deal came together

Hut 8 first announced the commercialization of Beacon Point’s initial phase back on May 6, 2026, when it secured a $9.8 billion lease covering 352 megawatts of capacity. That first lease alone carried options that could have grown its value to $25.1 billion.

Advertisement

Then on July 20, 2026, a second lease doubled the contracted capacity to 704 megawatts. The Financial Times and Reuters reported the full scope of the arrangement on July 28.

Across Hut 8’s entire AI infrastructure portfolio, total contracted IT capacity now sits at 949 megawatts with a base contract value of $26.6 billion.

Hut 8 used what it calls a “power-first model,” securing a 1,000 megawatt utility interconnection through AEP Texas before the data center was even fully built.

Nvidia plans to sublease portions of the facility to hyperscalers and cloud service providers.

From crypto miner to AI landlord

Hut 8 started life as a Bitcoin miner. The company spent years building out power infrastructure and cooling systems to run crypto mining rigs 24/7. That operational expertise, securing cheap energy, managing heat, maintaining uptime, turns out to be exactly what AI data centers need.

Hut 8’s stock reflected the market’s enthusiasm. Shares gained significantly following both lease announcements. When your biggest customer is a company worth nearly $5 trillion, the revenue visibility improves considerably.

Disclaimer: The information on this page may have been obtained from third parties and does not necessarily reflect the views or opinions of KuCoin. This content is provided for general informational purposes only, without any representation or warranty of any kind, nor shall it be construed as financial or investment advice. KuCoin shall not be liable for any errors or omissions, or for any outcomes resulting from the use of this information. Investments in digital assets can be risky. Please carefully evaluate the risks of a product and your risk tolerance based on your own financial circumstances. For more information, please refer to our Terms of Use and Risk Disclosure.