Microsoft Reduces $5 Billion in Capital Expenditure Amid Data Center Delays; Supermicro Raises Revenue Forecast

iconBitPush
Share
AI summary iconSummary
Microsoft reduced its Q3 capital expenditure by $5 billion due to delays in third-party data center projects, including Iren’s Texas facility. A UK project with Nscale was also abandoned due to grid access issues. Supermicro reported Q1 revenue of $19.95 billion, exceeding expectations, and raised its Q2 forecast to $19.5–21.5 billion. The company also increased its 2027 revenue outlook to $72–82 billion. The announcement comes ahead of key inflation data releases.

BlockBeats reports that Microsoft reduced its third-quarter capital expenditure by approximately $5 billion due to delays in the delivery of a third-party data center it planned to lease. According to The Information, sources familiar with the matter said the delay stemmed from the Iren data center project in Childress, Texas, causing Microsoft to postpone certain expenditures. Microsoft had previously announced plans to invest $9.7 billion over five years to lease Iren’s servers equipped with NVIDIA GPUs.

Power supply and grid access have also become bottlenecks in compute delivery. Last month, Microsoft withdrew from a plan to lease a data center project in the UK from Nscale due to delays in grid connection. As it is difficult to build its own data centers quickly enough to meet demand, Microsoft is simultaneously leasing compute resources from multiple cloud providers.

Meanwhile, AI server supplier Super Micro Computer (SMCI) continues to raise its earnings guidance. The company reported first-quarter revenue of $19.95 billion, exceeding analysts’ expectations of $16.39 billion, and forecasts second-quarter revenue between $19.5 billion and $21.5 billion. The fiscal 2027 revenue outlook has also been raised from $65 billion to $72 billion to $72 billion to $82 billion.

However, growth in server sales does not mean that computing power has been actually deployed. Bernstein notes that assessing AI computing demand cannot rely solely on contract value or megawatt scale; it must also consider contract cancellability, duration, and actual deployment timelines. Some data center projects may be delivered in phases over months or even years. Additionally, chip procurement agreements and data center leasing contracts may correspond to the same pool of computing power—counting them twice could overstate actual新增 computing demand.

This means that the bottleneck in the AI industry chain is extending from chip supply to data center construction, power supply, and computing power deployment. The time lag between growing server orders and final computing power delivery is worth noting.

Disclaimer: The information on this page may have been obtained from third parties and does not necessarily reflect the views or opinions of KuCoin. This content is provided for general informational purposes only, without any representation or warranty of any kind, nor shall it be construed as financial or investment advice. KuCoin shall not be liable for any errors or omissions, or for any outcomes resulting from the use of this information. Investments in digital assets can be risky. Please carefully evaluate the risks of a product and your risk tolerance based on your own financial circumstances. For more information, please refer to our Terms of Use and Risk Disclosure.